Tsuruga NRA Regional Office
Facilities to be inspected
- • Tsuruga Power Station, Japan Atomic Power Co., Inc.
- • Fast Breeder Reactor Monju, Japan Atomic Energy Agency
- • Fugen Decommissioning Engineering Center, Japan Atomic Energy Agency
Tsuruga Power Station, Japan Atomic Power Co., Inc.
Power Generation Facilities
Unit 1
- Reactor Type
- BWR
- Capacity
- 357 MWe
- Commissioning
- March 14, 1970
Unit 2
- Reactor Type
- PWR
- Capacity
- 1160 MWe
- Commissioning
- February 17, 1987
Present States of Operation
Fast Breeder Reactor Monju, Japan Atomic Energy Agency
Power Generation Facilities
- Reactor Type
- FBR
- Capacity
- 280 MWe
- Commissioning
- (First Criticality for Trial Operation, April 5, 1994)
Present States of Operation
Fugen Decommissioning Engineering Center, Japan Atomic Energy Agency
Power Generation Facilities
- Reactor Type
- ATR
- Capacity
- 165 MWe
- Commissioning
- March 20, 1979 (Termination of Operation, March 29 2003)
Present States of Operation
Location of the Nuclear Facilities
Tsuruga-shi, Fukui Prefecture
Address
Fukui Prefecture Tsuruga Nuclear Emergency Preparedness Center 1F,
99-11-47 Kanayama, Tsuruga-shi, Fukui, 914-0146
Phone: 0770-25-8661
Fax: 0770-25-8662
History
- •Tsuruga NRA Regional Office was established in September, 2012.